Uttarkashi Tunnel Collapse: Vertical drilling underway as rescue bid enters third week - How long is it likely to take?

Posted on:
Key Points

The fate of 41 workers trapped inside the Silkyara tunnel remained uncertain on Sunday as rescuers began the somewhat riskier process of vertical drilling..

Hope of an immediate rescue has faded after the auger machine encountered obstacles and broke down during horizontal drilling..

Without impediments it will take around 100 hours to reach the trapped workers from the top of the hill above the tunnel..

Vertical drilling started at around 12 noon. 86 meters of digging is required to reach the trapped workers and make an escape passage..

The Barkot end of the tunnel remains closed as work had not yet started on that side. . Officials are executing as many as six plans to rescue the workers..

You might be interested in

Uttarkashi tunnel collapse: Rescue ops put on hold again due to technical snag, 41 workers 'just metres away'

24, Nov, 23

The rescue operations to evacuate 41 workers trapped in Uttarakhand's Silkyara tunnel in Uttarkashi district has entered day 13 on Friday. Till now, rescuers have drilled up to 46.8 meters in the Silkyara tunnel

Uttarkashi tunnel collapse: Protests break out as falling debris hinders rescue of workers, bigger machine flown in

15, Nov, 23

Indian officials have contacted the Thai company which rescued the children trapped in the Tham Luang cave complex in 2018

Rescue efforts intensify for trapped workers in Uttarkashi's Silkyara tunnel

26, Nov, 23

The recovery of the damaged auger machine parts, obstructed during horizontal drilling, is in progress using magna and plasma cutters

No progress since Thursday, drilling to resume shortly: NDMA on Silkyara tunnel rescue ops

24, Nov, 23

By any means , the trapped workers will be rescued as all resources are being used, said NDMA member Lt Gen (retd) Syed Ata Hasnain while briefing media on rescue operations. There has been no progress in the movement of pipe through debris in the tunnel since Thursday, and about 15 metres of drilling is still left to reach the stranded workers, he added.

Uttarkashi tunnel rescue: Vertical drilling begins; mobile phones, board games given to trapped men to alleviate stress

26, Nov, 23

According to an India Today report, authorities on Sunday began vertical drilling on the hilltop above the Silkyara tunnel to create an alternate route for the trapped men to be rescued

Uttarakhand Silkyara Tunnel Rescue: Team faces another setback, digging halted after auger machine breaks

25, Nov, 23

Rescuers had been working by hand to remove debris after the drilling machine they were using broke down a day earlier while making its way through the debris of rock, stones and metal, but the operation was halted on Saturday.

Uttarkashi tunnel collapse: Experts from Norway, Thailand cave rescue roped in to save 40 trapped workers | 10 points

17, Nov, 23

Experts from Norway and Thailand were consulted for the challenging rescue operation in Uttarakhand, with 50 meters of debris needing to be penetrated for evacuation.

Five new plans to rescue trapped tunnel workers after a week of failed attempts

19, Nov, 23

Rescuers had been boring horizontally through the debris towards the trapped miners in the 4.5-kilometer (3-mile) tunnel until Friday, when the auger drilling machine broke and a new one had to be flown in

Uttarakhand tunnel collapse: Auger machine installed as rescue ops enter day 5

16, Nov, 23

It has been over 96 hours since workers have been stuck in the tunnel as rescuers are trying their best to execute their plans

Uttarkashi op: Vertical drilling makes progress, 5 more rescue plans in works

27, Nov, 23